A storm floods a building under construction, or a fire damages a project weeks before turnover. The repair bill is only part of the problem. The owner needs the building to open on schedule, the lender expects its deadlines to be met, and the contractor faces potential liability for delay. The crews work overtime, materials ship overnight, and unaffected work is resequenced to recover any of the lost time. But who pays for these costs?
Builders risk insurance may cover substantial portions of the recovery effort. Identifying the right coverage—and correctly documenting the additional spending—can determine whether the policyholder ultimately recovers.
Expediting Repairs Versus Accelerating the Project
After a loss, there is the ordinary cost to repair the damage, and then there are the extra costs of doing that work faster. Those extra costs typically include overtime, night and holiday shifts, air freight or express delivery, and adding crews or bringing in more contractors. Claims professionals usually call costs that speed up the repair of damaged property “expediting costs,” with the goal of shortening the delay. “Acceleration,” however, is a broader word. It often means speeding up the whole project to win back lost time, including work that was never damaged. That kind of cost is usually treated separately, often as “extra expense.” The difference between these two labels can decide whether an insured gets paid.
To determine coverage, policyholders must review the entire policy. Three areas deserve particular attention:
Repair and replacement coverage: Determine whether the expenditure forms part of the reasonable cost to restore or replace the damaged property. Insurers often say this means ordinary repair costs, not a premium for speed. Policyholders argue that a reasonable repair may require fast work when waiting would cause more damage.
Expediting and extra expense extensions: A typical builder’s risk form pays for overtime, night work, expedited shipping, or spending when the costs are incurred to expedite the repair or reconstruction of the damaged property. Often, this coverage does not reach work on undamaged parts of the project. However, some policies add a separate “extra expense” coverage for costs needed to keep undamaged work on schedule. Before making the claim, check whether costs must be incurred within a specified restoration period or whether separate sub-limits apply.
Delay and loss-reduction coverage: Delay-in-completion coverage may protect specified soft costs or lost income following insured damage. If you don’t have that add-on, or your costs don’t fit their definitions, you may end up paying this cost yourself.
A Recent Illustration
In a recent case out of the Northern District of Illinois, Walsh Construction Co. II, LLC v. Lexington Insurance Co., Walsh was building a tunnel under an all-risk builder’s risk policy. Two flood events stopped the work for months. Lexington paid some property damage costs but disputed Walsh’s claims for expediting and extra expenses.
The expediting expenses clause in the governing policy covered reasonable extra costs to expedite repair, “including additional wages for overtime, night work, work on public holidays and the extra costs of express freight.” The court found that costs to repair and reinforce damaged concrete was therefore covered under the policy. However, Walsh described part of its claim as “Accelerating to Recover Schedule After Dome Repair,” and included projected overtime to recover lost construction time, rather than actual repair expenditures. The court concluded that nothing in the relevant policy provisions said anything about acceleration costs or costs to recover lost time—and it was Walsh who specifically brought “acceleration” into the claim.
Walsh teaches us to distinguish each expenditure’s purpose and evaluate it under every potentially responsive provision, making clear what the incurred costs were for. A restriction in the expediting extension does not necessarily resolve whether separate extra expense coverage applies.
To Build a Strong Claim
Policyholders speed up work for good reasons. Every day that the building is closed adds to business income or rental losses. Construction contracts carry completion dates and liquidated damages. Sometimes fast action is needed to stop further harm. To strengthen a claim, policyholders should:
- Describe the work accurately. Explain whether spending expedites repairs, maintains undamaged work or reduces an insured financial loss.
- Document actual costs and timing. Support projections with invoices, payroll records and payment obligations as costs develop. Connect expenditures to any required coverage period.
- Preserve the schedule analysis. Retain pre-loss and recovery schedules, address unrelated delays and explain how the selected measures changed the expected outcome.
- Engage the insurer promptly. Give required notice, explain proposed measures, seek any necessary consent and document urgent decisions.
- Reconcile the submission. Ensure each claimed expenditure appears in the supporting records and is evaluated under the appropriate provision.
Conclusion
The insurer generally pays reasonable costs to speed up repair of damaged property within any sublimits. Costs to win back lost schedule are recoverable only if coverage like extra expenses or delay in completion reaches them. Read the policy, track actual costs, describe those costs accurately, and send each cost to the coverage built for it. Qualified coverage counsel can help make sure opportunities to recover aren’t missed. That way speed isn’t an expense you fully pay for yourself.